Site Improvements ($2,229,666)

  • Stadium Improvements and Turf Replacement
  • Turf Field Drainage Improvements
  • Access Road Repaving to Sulphur Springs
  • Resurfacing of Track and Associated Areas
  • Middle School Tennis Courts Surfacing Repairs
  • Middle School Accessible Ramp to Softball Fields Area Bleachers
     

Roof Replacements ($2,653,410)

  • High School (11,000 SF)
  • Middle School (Entire Roof: 42,500 SF)
  • Elementary School (2,003 SF)
  • Bus Garage (Entire Roof - Except Area Above Offices: 15,100 SF)
     

Flooring ($1,539,900)

High School

    • Replace rubber tile at vestibule
    • Classroom kitchen flooring replacement


Middle School

    • Replace existing floor with new resilient tiles (Selected Rooms)
    • Replace existing corridors, vestibules, lobbies and staircase floors with new epoxy terrazzo.
       

Elementary School

    • Replace corridor floor tile
    • Refinish gym wood floors
    • Replace existing floor with new resilient tiles (Selected Rooms)
       

Mechanical Upgrades ($1,728,950)


High School

    • Ventilation upgrades throughout building
       

Middle School

    • Gymnasium ventilation upgrades
       

Elementary School

    • Ventilation upgrades throughout building
       

Bus Garage

    • Heating and ventilation upgrades
       

Other Key Upgrades

High School

    • Boys and Girls Locker Room: Minor renovations for gender neutral changing areas
    • Exterior Brick Masonry Repointing / Repairs / Replacements
    • Upgrade elevators and controls
    • Plumbing Replacements
       

Middle School

    • Boys and Girls Locker Room: Minor renovations for gender neutral changing areas
    • Exterior Brick Masonry and Chimney Repointing
    • Plumbing Replacements
       

Elementary School

    • Exterior Brick Masonry Repointing / Repairs / Replacements
    • Plumbing Replacement